• Uwchlan Hills Elementary School Project

    • On December 11, 2017 the Board of Directors approved the construction of a new Uwchlan Hills Elementary School.
    • The School Board approved all prime contractors at its meeting on March 13, 2019.
    • Basement walls are being poured and formed on the lower stair tower and equipment storage area.
    • Site contractor has finished the sewer piping installation to the building mid-section.
    • The EC is installing his primary electric feeder ducts from the street to the building and encasing them in concrete.
    • Steel has arrived and has begun to be set, which will continue through the end of September.

                  Artist drawing of UHES             UHES Basement Walls and Steel Construction

                               Artist Rendering of UHES                                                  Photo of construction underway